RISK 01: Time management issues Risk Description: Underestimating how much effort is needed to complete a task or overestimating how much time each team member has available to work on the project may lead to delays, missed deadlines or even development gaps.

Risk Evaluation

Impact:     🞆1(Very Low)  🞆2(Low)  ****🞆3(Average)  🞆4(High)  ∎5(Very High)

If the time invested in a task is significantly lower than the actual time needed to complete it properly it leads to either an incomplete implementation or a low quality solution.


Probability: 🞆1(Very Low)  🞆2(Low)  🞆3(Average)  ****∎4(High)  🞆5(Very High)

Explanation: The team has little experience in estimating this level of tasks with varying levels of complexity. Also many other variables from daily life can affect the previously estimated schedule.


Risk Response Plan

Prevention Tasks:

To avoid the risk of time management issues, we held several meetings in which various processes for the development of the project were carried out so that possible scenarios were analyzed, and thus better managed the time for distributing tasks while also using methods such as "planning poker" to achieve better estimations. We are also using advanced project management tools such as Jira to help us ensure we stay on track by visualizing progress and enabling precise task management.

Mitigation Tasks:

The strategy to reduce the impact of poor time management of activities will be by applying 30% above the stipulated time for each project activity.

Re-evaluated Impact (1~5): 3 Re-evaluated Probability (1-5): 2

RISK 02: APIs may be too demanding for Raspberry Pi 4 Risk Description: APIs might run slowly or even not work at all due to limited hardware.

Risk Evaluation

Impact:       🞆1(Very Low)  🞆2(Low)  ****🞆3(Average)  ∎4(High)  🞆5(Very High)

Explanation: Without the APIs there will be no transcription from audio to text and from text to audio, therefore there will be no communication between the user and the device.